Show transcribed image text PW of Project A is -$10,000 PW of Project B is -$20,000 PW of Project C is $30,000 All of the projects are independent projects and are not mutually exclusive. Assuming that the budget is unlimited, which project(s) should be selected? Project C Projects B and C Projects A and C Project A Projects A and B Project B Projects A, B, and C

PW of Project A is -$10,000 PW of Project B is -$20,000 PW of Project C is $30,000 All of the projects are independent projects and are not mutually exclusive. Assuming that the budget is unlimited, which project(s) should be selected? Project C Projects B and C Projects A and C Project A Projects A and B Project B Projects A, B, and C