28. Given an auditing project with the following Activity Std. Dev. Critica Duration (wks) a. Add b. BalanceI c. Count d. Deduct e. Edit f. Finance g Group 2 h. Hold Using the critical path, find a. The probability of completing this project in 12 b. The probability of completing this project in 13 c. The probability of completing this project in 16 d. The number of weeks required to assure a 925 weeks or less, as the client desires weeks or less. weeks or less, the client's drop-dead date percent chance of completion, as guaranteed by the auditing firm.