550 products are required per week. The operation runs 8 hours,
4 days per week. The assembly steps and times for this product are
given below. Answer the following 3
questions.
Task | Time required |
Wash | 4 minutes |
Dry | 3 minutes |
Box | 1 minutes |
Weld | 5 minutes |
Assemble | 3 minutes |
Paint | 2 minutes |
Grind | 3 minutes |
Refer to the above information: what is the workstation cycle time?
(The format of your answer should keep two decimal places, for
example, 4.35)