A Project Manager is managing a project to upgrade the security
system of a large retail organization. When creating the schedule,
the PM decided that there would have to be a 3 day delay for the
security system to be certified before the new system can be
activated. Which of the following describes what the PM
decided?
Select one:
a. A start to start relationship
b. A lead
c. A finish to finish dependency
d. A lag